RM12-Old Kyle Road improvements project set for January-February

Posted By on December 9, 2012

The Texas Department of Transportation has opened the bids for work on the Square and Old Kyle Road-RM12 intersection and expects to award a contract for the work by the end of the month.  If that schedule holds, TxDOT expects work to begin around the end of January and to take 30 to 35 days.  The work is planned for the “slow” visitor period downtown to minimize the impact on downtown merchants.